About the project
A complete reconstruction has been carried out
The design, general construction and finishing works were completed on time. All engineering communications of the building were replaced (ventilation, power supply and sewerage)
WORK COMPLETED
Facades
More details
Engineering
More details
Heating
More details
Интерьер
More details
Water supply sewerage
More details
Fire precautions
More details
Seismic safety of the building
More details
Audiences
More details
Improvements for people with limited mobility (PLM)
More details
Facades
Ventilated facade with metal cassettes and artificial stone “Euro-stone”;
Aluminum double-chamber stained-glass windows and windows with energy-saving multifunctional double-glazed windows were installed;
Waterproofing of the basement walls was carried out with an increase in the height of the basement floor;
An all-metal roof has been installed;
An additional 6th floor with classrooms has been built;
The building's load-bearing structures were strengthened by constructing vertical portal connections from steel elements;
The existing reinforced concrete columns, adjacent to the steel ties, were framed with steel frames of four equal-flange angles, ensuring the complete reliability of the building;
The main entrance to the academic building was reconstructed, taking into account the external climatic conditions, insulation and ventilation were carried out;
External faсade lighting has been installed.
Engineering
A ventilation system was installed in each room in accordance with the standards of the Republic of Kazakhstan (VTS Poland);
The air conditioning system was set up in the administrative premises and in the continuous classrooms on the 6th floor (Daikin);
New elevators with a maximum load capacity of 1000 kg, suitable for PLM, have been installed;
A new transformer substation (TS) was installed - 1 pc. (1100 kW);
More than 22,000 linear meters were stretched. copper cables;
The lighting was replaced with designer LED lamps;
Electrical installation equipment from the European brand – Legrand was introduced;
The smoke removal system has been configured in accordance with the standards of the RoK.
Water supply sewerage
3 booster pumps were installed. and fire pumps in the amount of 2 pieces;
Input of water from 2 main pipes in accordance with the standards of the Republic of Kazakhstan;
Fire hydrants were installed - 177 sets;
The internal water supply and sewerage system was completely replaced;
Bathrooms for people with limited mobility (PLM) have been taken into account;
Cleaning equipment premises (CEP) for service personnel are taken into account;
All bathrooms have been updated with the replacement of plumbing fixtures.
Heating
Horizontal heating installation completed
with division for each block – 100% updated;
A block heat station (BTP) was installed - EnCo LLP - 100% updated;
New distribution collector units (DCU) were installed – 31 pcs.;
New bimetallic radiators with adjustment were installed.
Fire precautions
Fire compartments on each floor in accordance with the standards of the RoK;
Fire doors were installed on each floor - El60;
A fire curtain was installed on the 1st floor;
All emergency exits with anti-panic doors have been reconstructed.
Seismic safety of the building
The building was seismically strengthened by strengthening the structure with metal dampers on all floors;
Expansion joints were made and the building was divided into 3 blocks;
Anti-seismic joints are made by installing steel consoles under the floor slabs of each tier and then cutting the slabs in cells with a span of 3 m in the middle of the span with a gap between them of at least 5 cm.
Interior
The interior has been updated using high-quality finishing materials: porcelain stoneware, quartz vinyl tiles, carpet, acoustic panels, increased strength;
Recreation facilities for students and teaching staff (STS) were updated;
The lighting was replaced with modern LED lamps;
A complete renovation of the dining room equipment and an increase in seating were carried out;
A coworking area and smart libraries were built;
A science center with a separate entrance was built;
The classrooms were equipped with interactive panels;
On the territory of the educational building there are 3 additional cafe areas, with cozy seats and free boarding access.
Audiences
The number of streaming audiences has been increased to 8;
The number of seats has been increased to 192 and 204;
An independent ventilation system was installed;
Acoustic panels were installed in each streaming auditorium;
Conditions for comfortable lighting have been created for the educational process;
An independent air conditioning system was installed;
Installed online and offline video-acoustic systems;
Seats are provided for people with limited mobility (PLM).
Improvements for people with limited mobility (PLM)
Separate bathrooms for PLM;
Creating unhindered movement throughout the building;
Creating an inclusive space;
All doorways are made without a threshold, for the unhindered movement of people with disabilities;
Freight and passenger elevators for 1000 kg;
In the continuous classrooms on the 6th floor, seats for PLM are taken into account.
Quality control
Throughout the entire period, the work of key specialists as part of the working commission was carried out. Work with the State Commission.
Renderings of the reconstruction project and photographs of the facility upon completion of construction and installation work
PHOTO GALLERY
FREE CONSULTATION
We can consult you for free on any issue
Leave your contacts below and we will contact you shortly
By clicking the "Send" button, you consent to the processing of personal data
© 2023 VERUM Construction
Request a call